Thursday, November 6, 2008

Third Thursday


We were all at the Pitman Vermont House today. The team had completed all of the changes required by the inspection by the end of the day Wednesday.

An additional inspection was completed today so we could progress full speed. The team was divided up into groups and each given a room to insulate and sheet rock. We are using batts of insulation in the ceiling. In the Waxman they are going to blow in insulation into the attic. The walls are also insulated because of air conditioning and some heating.

We have also continued with the siding. We painted it before we put it up and it looks great.

Today we finished the insulation. We have one about 60 % of the ceilings sheet rocked and expect to finish all of it tomorrow. If time permits we will begin mudding the walls.